The District had only one submitted bid for the project, although 3 bidders had expressed interest in the project. Trustee Dent inquired as to the reasons and staff stated it had to do with the difficulty of the project due to access to the locker rooms. The bid was higher than the engineer’s estimate resulting in the need for the board to augment the budget. The total estimated costs of the project, including staff time and a 10% contingency, is $975,843. The board approved in a 4-1 vote with Trustee Dent opposing. Construction is expected to begin on May 2nd. Click here to view the details.
TTD Incline Village Mobility Committee Meeting
TTD Incline Village Mobility Committee Meeting
Mon Feb 27 - 5:30 pm at Incline Village Library, 845 Alder Avenue, Incline Village, NV Agenda discussion items include: Review and Discuss the Schedule for the Incline Mobility Hub Project Concepts and Public Involvement Plan Process and Next Steps for Stakeholder Engagement Review of Changes to California’s Meeting Requirements for Public Agencies Subject to […]