The storage tank proposed for the WRRF is 99 feet in diameter, 40 feet high and holds 2 million gallons. Concrete panels will be formed on-site, then placed in position...
IVGID Projects – Neighborhood Meetings
On Tuesday, August 16th, beginning at 6 p.m., two neighborhood meetings will be held to solicit community input on IVGID's proposed Bike Park Phase II and the Effluent...
Pipeline Design Contract Moves Forward & Update on Potential Funding
The Trustees voted unanimously to approve Amendment 2 for additional Professional Services associated with the Effluent Export Pipeline project, in an amount of $322, 588...
Water and Sewer Rate Study
The IVGID Board of Trustees was asked 1) to approve proposed rate increases and fee schedules for sewer and water, based, in large part, on a the draft HDR Utility Rate...
IVGID Consent Calendar Items Approved
At the IVIGD Board of Trustees meeting held on Wednesday, March 9th, the Board unanimously approved the consent calendar including the following items: The purchase of new...
IVGID BOT Meeting Highlights
The IVGID Board of Trustees met virtually on March 1, 2022. Director of Finance Paul Navazio updated the Trustees on financials for the second quarter of Fiscal Year...
IVGID Meeting Highlights
The Tahoe Daily Tribune summarized the meeting held on February 9th, however in doing so they didn't accurately reflect the increases proposed for the water and sewer rates...
County Update
Washoe County is in discussion with IVGID regarding the potential allocation of some of Washoe County's funds from the American Rescue Plan Act of 2021 (ARPA) funds to...
Another Break In Our Pipeline
The Effluent Pipeline – Another Failure Once again there has been a failure of the yet to be replaced 50+ year old section of the effluent pipeline that runs under SR28...
Yes, It Failed Again – Effluent Pipeline Break Information
There has been another failure of the yet to be replaced 50+ year old section of the effluent pipeline that runs under SR28 between Sand Harbor and Spooner Summit. This...
Effluent Pipeline Phase II
Seven years after the District began collecting $2M annually from ratepayers to fund the $23M replacement of the remaining 6 miles of our effluent pipeline NO activities for...